Gas Main Diversion at A14 Dual Carriageway

GAS MAIN DIVERSION AT A14 DUAL CARRIAGEWAY

Excavation works began in 2017 for the construction of a thrust wall to Auger Bore, to allow for the diversion of a gas main on Highways England’s £1.5billion A14 Dual Carriageway Cambridge to Huntingdon Improvement Scheme.

This project includes both road widening and construction of a new stretch of road to help relieve congestion between the Girton Interchange and Brampton Hut. The four-year project is due to be completed in 2020.

PROJECT

Gas Main Diversion at A14 Dual Carriageway

Contractor

A14 Integrated delivery team

Project Lead

Hannah Hamilton, Area Sales & Regional Account Manager

KEY BENEFIT

A fast turnaround was delivered with on site training on how to use MGF equipment

THE SOLUTION

The excavation was a short distance from the existing A14, which remained open whilst work was carried out. The ground conditions in the area where stiff clay and therefore raised concerns of achieving a suitable toe length to allow for a propped cantilevered design.

To overcome this issue MGF provided a full temporary works design for a slit trench installation method that would use a modest toe on the sheets along with multiple levels of frame.

A14 Dual Carriageway 2

THE VERDICT

Working closely with the main contractor (the A14 Integrated Delivery Team), subcontractor and installation team, the frames were then built at our depot in East Anglia which allowed us to give the customer a faster turnaround and consisted of two levels of 203UC Brace – a heavy duty hydraulic bracing system with a double acting hydraulic power pack, that was combined with 3m and 0.6m extensions to form the leg brace.

FKD Trench Sheets where also provided along with MGF Laddersafe and MGF Davitsafe to allow safe access and egress of operatives into the excavation.

Additional support was given by Hannah Hamilton, who presented an in- depth tool box talk to the installation team prior to the installation of kit and was on hand with support throughout.

Related Products

FKD 4006

Trench Sheets – FKD 400/6 (S275 JRC)

Trench sheets provide an effective ground solution to support the vertical faces of trenches and excavations. Galvanising service Available lengths: …

Laddersafe

A gated ladder access platform available in a variety of formats that allow it to quickly and effectively clamp to …

203 product image

203 UC Brace

Designed to brace small to medium sized cofferdams as well as larger trenches, this system allows for the safe installation …

Get in touch

Whether you have a question, need a quote, or want to discuss a project, our dedicated team is ready to assist you.

Search...